FG Suspends Aseese Bridge Construction After 22-Hour Lagos-Ibadan Gridlock
FG Suspends Aseese Bridge Construction After 22-Hour Lagos-Ibadan Gridlock

The Federal Government has suspended the ongoing construction of a pedestrian bridge at Aseese, along the Lagos-Ibadan Expressway, following a prolonged traffic gridlock that left motorists and commuters stranded for more than 20 hours.
The construction project, being handled by the Federal Ministry of Works in collaboration with CBC Construction Company, commenced on Wednesday, November 18, with a temporary traffic diversion introduced to facilitate the installation of the pedestrian bridge.
However, the diversion triggered severe congestion along the expressway, with traffic reportedly building up from about 2 p.m. on Wednesday and persisting until Thursday afternoon. Several commuters were forced to abandon their vehicles and trek considerable distances, while others spent several hours covering relatively short journeys.
The situation also resulted in increased transport fares, with some commercial drivers and motorcycle operators reportedly charging significantly higher rates to convey stranded passengers.
President Bola Tinubu’s Special Adviser on Media and Communications, Sunday Dare, had earlier criticised the timing of the construction, questioning why the work was not scheduled for periods of lighter traffic to minimise hardship for road users.
Following the disruption, the Ogun State Traffic Compliance and Enforcement Agency (TRACE) announced the indefinite suspension of the construction work and its associated traffic diversion.
TRACE spokesperson, Babatunde Akinbiyi, explained that the decision became necessary after the significant traffic challenges experienced along the corridor. The acting Controller of the Federal Ministry of Works in Ogun State, Richard Adeleye, also confirmed that the suspension was due to the traffic situation.
The agency apologised to motorists and other road users for the inconvenience, adding that further updates would be communicated when there are new developments regarding the project’s resumption.
The development has renewed calls for improved traffic management and proper scheduling of road construction activities, particularly along major highways, to prevent infrastructure projects from causing unnecessary hardship for commuters.